QC acceptance

Acceptance criteria.

The numbers that decide whether a delivery is accepted or rejected — fresh-concrete tolerances, strength acceptance, discharge window, mass-concrete temperature.

IS 516:2021 + IS 456:2000

Four numbers decide each load.

The rules of acceptance are defined by IS 516:2021 (testing) and IS 456:2000 (compliance). Kalokhe RMC works to tighter internal limits than the standards require, so every dispatched load starts with margin on its side.

01 Workability slump · flow
02 Discharge window batching → truck → chute
03 Temperature ≤ 32 °C standard · ≤ 26 °C mass
04 Strength 7 d & 28 d cubes
Spec sheet

The four numbers, side by side.

Slump tolerance
± 25 mm
OR ± 1/3 of specified slump — whichever is lower. Examples: 60 mm → ±20 mm; 100 mm → ±25 mm; 150 mm → ±25 mm.
Flow (SCC)
± 80 mm
For a 600 mm specified flow, the acceptable range is 520 – 680 mm. Run the J-ring test in parallel for aggregate blocking.
Discharge window
≤ 180 min
From batching to start of discharge per IS 516:2021. Reduce in hot weather; extend only when retarder design and tests allow.
Mass concrete
≤ 26 °C
Pour temperature cap for mass concrete (≤ 32 °C for normal members, ≥ 5 °C minimum). Reduce via chilled water / GGBS blends.
Tolerances

Acceptable ranges at a glance.

How the four limits translate into minimum and maximum bound values.

Lower bar 75 mm slump = 100 ± 25 mm. Flow bounds 520 – 680 mm. Discharge 0 – 180 min. Normal delivery temperature 5 – 32 °C. Mass-concrete ≤ 26 °C.

IS 456:2000

Compressive-strength acceptance.

Group result · ≥ 4 samples Mean and individual
  • Mean of 4 consecutive samples ≥ fck + 0.825 σ (σ from ≥ 30 prior samples)
  • OR Mean ≥ fck + 3 MPa if σ is not established
  • AND every individual sample ≥ fck − 3 MPa (or 0.85 fck when fck < 20)
Individual result · < 4 samples Single sample rule
  • Each sample ≥ fck + 4 MPa
  • For fck < 20 MPa: sample ≥ fck + 0.825 σ
  • Average of two cubes from the same sample constitutes one test result
Reject

Four grounds for rejection.

Any one of these conditions means the load is rejected at site — Kalokhe RMC replaces rejected trucks at no charge.

Time exceeded Discharge window > 180 min From batching to start of discharge — IS 516:2021 limit, tighter in hot weather.
Temperature exceeded > 32 °C normal · > 26 °C mass Out of tolerance at delivery — heat is one of the largest strength-killers on a hot pour.
Segregation Visible aggregate separation Coarse piles to one side, paste runs free, the mix has lost homogeneity — placement will create rock pockets.
Workability outside ±tolerance Slump · flow outside limits Outside ±25 mm / 1/3 of specified slump, or ±80 mm flow. Retempering on site is not permitted.
Pre-pour

Pre-acceptance checklist.

Before acceptance At the chute.
  • Challan matches order — grade, slump, admixture spec.
  • Truck within batching-to-discharge window.
  • Slump test passes tolerance; record value.
  • Concrete temperature within limit.
  • Visual check — no segregation, bleeding, or foreign matter.
  • Cubes cast per sampling frequency.
Records to keep Documentation.
  • Delivery challan — signed at site.
  • Slump and temperature record card.
  • Cube-casting register — date, location, grade, sample ID.
  • 7-day and 28-day cube test reports.
  • Rejection reports if any — with photographs.
  • Site engineer signature on every record.